CAVITEX southbound lane to temporarily close starting Sept. 15 as LRT-1 extension works resume

Robie de Guzman   •   September 8, 2020   •   757

MANILA, Philippines – A lane along CAVITEX southbound near Parañaque bridge will be temporarily closed to motorists starting Sept. 15 to give way to the resumption of the construction works for the Light Rail Transit line 1 (LRT-1) Extension project, the Light Rail Manila Corporation (LRMC) announced.

In an advisory on Monday, the LRMC said the lane closure will be implemented until Dec. 15, 2020 for the pipe relocation works by Maynilad which relative to the construction activities for the 11.7-kilometer LRT-1 Cavite Extension Project.

This is a follow-through of the test pit works (bridge and pipe inspection) which was conducted in the same area last May 2020, the LRMC added.

In line with the lane closure, the agency asked motorists for understanding and advised them to plan their trips ahead.

“We are aware that this will bring temporary inconvenience. But once the project is completed, travel between Baclaran and Bacoor will be faster, easier, and more convenient for our commuters,” LRMC Cavite Extension Management Team (CEMT) Project Execution Manager Reynaldo Pangilinan said.

The LRMC said that since the start of the civil works in September 2019, the project’s percentage completion rate has reached 40% for the project aspects within the agency’s scope.

The agency revealed that the Cavite Extension project makes use of an above-ground launcher, a special engineering method, to allow for faster execution and minimal effect on the ground-level traffic. The viaducts are transported above-ground instead of street-level.

“Despite the limitations brought by the quarantine period and the necessary adjustments, we have been able to make progress on this project,” Pangilinan said.

The Department of Transportation earlier said the project will extend the existing LRT line 1 from Baclaran to Niog in Bacoor, Cavite and is envisioned to shorten the travel time from Manila to Cavite to 25 minutes from the current one hour and 10 minutes.

LRT-1 releases train schedules as NCR reverts to ECQ status

Maris Federez   •   March 28, 2021

 

MANILA, Philippines—The Light Rail Manila Corporation has adjusted the train service hours it will apply to LRT-1 in light of the government’s move placing the NCR and surrounding provinces under enhanced community quarantine and for the long holiday break.

For March 29 to 30, the first trip will leave at 4:30 in the morning from both start-off stations in Baclaran, Parañaque and in Balintawak, Quezon City.  The last trip, on the other hand, will leave Baclaran at 9:30 PM and 9:45 PM from Balintawak.

LRT-1 operations will be suspended from March 31 to April 4 to give way to maintenance activities during the long holiday.

Regular train schedules will resume on the following Monday, April 5, from 4:30 AM to 9:15 PM from Baclaran and 9:30 PM from Balintawak.

“The shortened operating hours from April 5, 2021 onwards will also allow LRMC to perform safety and integration tests for the upgrading of the LRT-1 signaling system, as well as prepare for the commercial run of our new Gen-4 trains in the last quarter of the year,” the LRMC said.

The LRT management also said that Roosevelt station remains temporarily closed, giving way to construction works at the Unified Grand Central Station on North Ave.—mbmf

Please take note of the #LRT1 train service schedule during Holy Week. 🚊

In order to facilitate necessary upgrades and…

Posted by Light Rail Manila Corporation on Monday, March 22, 2021

 

DOTr unveils first batch of new trains for LRT-1 Cavite extension project

Robie de Guzman   •   January 27, 2021

MANILA, Philippines – The Department of Transportation (DOTr) has unveiled the first batch of new trains that will be deployed for the Light Rail Transit line 1 (LRT-1) Cavite Extension project.

The four new train cars, which were ordered from Spain and Mexico, were presented on Tuesday, January 26.

These are part of the 120 train cars that will form 30 four-car trains that can accommodate up to 750,000 passengers daily. The LRT-1 currently serves 500,000 commuters daily.

“This fourth generation of Light Rail Vehicles will more than doubled the number of operations LRVS of LRT from 86 LRVs IN 2016 up to 192 LRVs by 2022,” Transportation Undersecretary Timothy John Batan said.

The DOTr said the new train cars feature more allotment areas for passengers and better cooling fans that will help lengthen the service life of the cooling system.

Once the delivery of new trains is complete, the LRT-1 will have 48 train sets from the current 34 train sets.

According to Light Rail Manila Corporation (LRMC), which operates the LRT-1, the construction of the Cavite extension project is now 50% percent complete.

Transportation Secretary Arthur Tugade is eyeing partial operability of the LRT-1 extension project by the fourth quarter of this year.

“I asked the rail sector and I asked the LRTA and the LRMC to make sure that partially operability of this project can materialize by December of this year. I don’t mind hitting 1 or 2 stations but scot to be partially operational,” Tugade said.

The LRT-1 Cavite extension project will stretch across Baclaran to Niog in Bacoor, Cavite. Upon completion, travel time from Manila to Cavite will be trimmed down to just 25 minutes, from the current 1 hour and 10 minutes.

The project was funded through a loan extended by the Japan International Cooperation Agency. – RRD (with details from Correspondent Joan Nano)

CAVITEx opens 3 additional lanes to ease traffic flow

Marje Pelayo   •   December 3, 2020

MANILA, Philippines — The Cavite Expressway (CAVITEx) management has temporarily opened three additional lanes to ease the flow of traffic south of Metro Manila.

Since December 1, motorists have been allowed to ply the newly constructed Parañaque, Wawa, and Las Piñas bridges that are part of the CAVITEx R1 Bridge Widening Project. 

The CAVITEx management reminds motorists to be extra cautious in using the said roads to prevent accidents and inconveniences.

Motorists may contact the CAVITEx management at Hotline numbers (02) 165-8888 in case of concerns and emergencies.

REACH US

The Philippine Broadcast Hub

UNTV, 915 Barangay Philam,

EDSA, Quezon City M.M. 1104

(+632) 8396-8688 (Tel)

info@untv-newsandrescue.com (General inquiries)

ABOUT UNTV

UNTV is a major TV broadcast network with 24-hour programming. An Ultra High Frequency station with strong brand content that appeal to everyone, UNTV is one of the most trusted and successful Philippine networks that guarantees wholesome and quality viewing experience.